PROJ 586 Week 8 Final Exam,
1. (TCO A) In the _____ organization structure, the project manager is responsible for the project results, whereas the functional manager is responsible for providing the resources needed to achieve the results. (Points : 5)
mixed-mode
matrix
autonomous project
functional
1. (TCO A) In the _____ organization structure, the project manager is responsible for the project results, whereas the functional manager is responsible for providing the resources needed to achieve the results. (Points : 5)
mixed-mode
matrix
autonomous project
functional
2. (TCO H) What is the longest phase of the project life cycle? (Points : 5)
Initiating
Planning
Performing
Closing
Initiating
Planning
Performing
Closing
3. (TCO B) The lowest level item of any one branch of the WBS is called a(n) _____. (Points : 5)
object item
task statement
work package
activity node
object item
task statement
work package
activity node
4. (TCO D) A _____ is a predefined set of actions that will be implemented if the risk event occurs. (Points : 5)
management proposal
classification array
contingency plan
risk contingency matrix
management proposal
classification array
contingency plan
risk contingency matrix
5. (TCO F) _____ the project involves measuring actual progress and comparing it to planned progress. (Points : 5)
Planning
Scheduling
Forecasting
Controlling
Planning
Scheduling
Forecasting
Controlling
6. (TCO C) If _____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing the completion of the project by its required completion time. (Points : 5)
total time
free time
total slack
cumulative slack
total time
free time
total slack
cumulative slack
7. (TCO G) Which of the following is not an advantage of using project management software? (Points : 5)
Accuracy
The learning curve
Speed
Record keeping
Accuracy
The learning curve
Speed
Record keeping
8. (TCO A) Which of the following is not an example of a project? (Points : 5)
Starting up a restaurant
Creating a website for a company
Raising money for a disaster-relief trip
Emptying the recycling everyday
Starting up a restaurant
Creating a website for a company
Raising money for a disaster-relief trip
Emptying the recycling everyday